Gross economic returns from the BP, before the investor’s personal taxation and before project exit taxation, which remains to be documented. Fiscalite_Nette variants are not a secured final net return.

Severe combined stress · assumptions and corrective funding

Revenue at 72% of scenario, variable costs at 82%, fixed costs +5%, rates +100 basis points. 2029 DSCR: 0.52×; corrective funding to restore 1.25×: €103,229.

Uncommitted €200k standby, separate from the optional €100k VAT facility. The prudent six-month opening-delay stress requires €320,465, below opening cash headroom of €356,616 above the €150k floor. In isolation, it is absorbed without a new contribution or standby facility; stresses are not assumed to occur simultaneously.

Le Sirius

Data Room · Le Sirius Bar-sur-Loup · 10 · 2026

Financial analysisA new concept · Luxury · Intimacy · Advanced wellness

November 2026 reference: updated roadmap and funding

Target fundraising closing in January 2027; acquisition and works in February; opening on 1 July 2027. €2m entirely in preference shares for 50% of the holding company. Total funding: €3.875m, including €1.870m senior debt and €5k founder capital. No investor shareholder loan.

YearRevenue excl. VATEBITDADSCR
2027396,028 EUR94,044 EUR1.18×
20281,103,519 EUR463,109 EUR4.27×
20291,183,979 EUR479,592 EUR3.05×
20301,226,540 EUR490,641 EUR3.03×
20311,267,717 EUR500,214 EUR3.08×
20321,313,387 EUR521,049 EUR3.19×
20331,353,501 EUR537,148 EUR3.28×
20341,398,170 EUR556,219 EUR3.38×
20351,442,276 EUR574,343 EUR3.48×
20361,474,144 EUR582,681 EUR3.52×
Pilot returns and distributions
ExitMOICGross IRRCumulative distributionsExit proceeds
20312.14×17.29 %1,058,359 EUR3,216,946 EUR
20332.59×16.48 %1,736,716 EUR3,436,967 EUR
20363.31×15.83 %2,671,854 EUR3,949,852 EUR

2027 includes six operating months. BP occupancy for 2027 retains a theoretical base including closed May and June: 33.42%, versus 44.51% over the 920 available room-nights from July to December. Revenue remains as modelled in the BP. Gross returns before personal tax and project exit taxation still to be documented.

Financing structure, debt, banking ratios and stress tests: a clear investor view of project economics and principal sensitivities.

€1.870msenior debt
modelled
56.7%LTV
on target value
2.30xPrudent DSCR
stabilised
€196.4kminimum cash
modelled
01

Executive overview

Balanced financing with contained leverage

The plan combines €2.005m equity and quasi-equity with €1.870m senior debt. Stabilised debt coverage exceeds the stated benchmarks, while liquidity and property value remain the two main monitoring priorities.

Structure

Balance

48 / 52

An almost equal split between equity and senior debt.

Leverage

Moderation

0.93x

Debt represents 0.93 times the project’s equity and quasi-equity.

Coverage

Banking headroom

2.30x

Stabilised DSCR exceeds the 1.25× benchmark.

Liquidity

Discipline

€150k

€150k cash threshold; projected prudent minimum of €196.4k with VAT refunds at M+2.

InterpretationConditional ratios

Indicators rely on the financial plan’s assumptions, including a €3.3m post-works property value. They are an analytical basis, not a financing or performance guarantee.

Portrait of Malika
House Manager
« Financial discipline starts with a consistent view of funding, uses, cash and alert thresholds. »
Malika
02

Sources & uses

€3.875m allocated to a clear plan

Equity & quasi-equity€2.005m51.7% of financing
Senior debt€1.870m48.3% of financing

Funding sources

SourceAmountShareType
Preference shares€2,000,00051.6%Investor equity
Founders’ capital€5,0000.1%Nominal capital
Senior debt€1,870,00048.3%Bank financing
Total funding€3,875,000100.0%Balanced plan

Uses

UseAmountShare
Acquisition€2,500,00069.9%
Notary fees€182,2925.1%
Works€400,00011.2%
Furniture€100,0002.8%
Launch, fees, working capital and reserve€395,70811.1%
Total uses€3,875,000100.0%
Equity & quasi-equity · 51.7%Senior debt · 48.3%

“Launch, fees, working capital and reserve” combines pre-opening, structuring, banking fees, working capital and interest reserve. Sources and uses balance at €3.875m.

03

Senior debt

Long-term debt without a bullet repayment

Amount€1.870mAcquisition and works
Nominal interest rate4.25%Fixed-rate assumption
Term25 years300 months
Grace period24 monthsPrincipal only
Final maturityNo balloonFull amortisation
2.30x

At stabilisation, projected coverage exceeds the 1.25× benchmark. The principal grace period supports works and initial ramp-up, after which debt amortises fully over its term.

These parameters reflect the financial scenario presented and remain subject to final banking offers and documentation.

04

Banking ratios

Levels consistent with the stated benchmarks

RatioFormulaValueBenchmarkAssessment
LTVDebt / property value56.7%< 60%Within benchmark
LTCDebt / total cost48.3%< 65%Within benchmark
LeverageDebt / equity0.93x< 2.00×Moderate
Equity and quasi-equityEquity and quasi-equity / total cost51.7%> 40%Robust
2027 DSCRCFADS / debt service1.83x> 1.25×Covered
2028 consolidated DSCRCFADS / debt service3.02x> 1.25×Covered
Stabilised DSCRCFADS / debt service2.30x> 1.25×Covered
LTV1.870 ÷ 3.300 = 56.7%

The €3.3m property value is a post-works assumption subject to appraisal.

LTC1.870 ÷ 3.875 = 48.3%

Debt finances slightly less than half the total project cost.

Equity2.005 ÷ 3.875 = 51.7%

The equity and quasi-equity contribution limits initial financial leverage.

Portrait of Pierre
Architect · Works & property
« Post-works value requires independent confirmation and does not replace cost and execution control. »
Pierre
05

Stress tests

Prudent scenarios retain coverage headroom

The matrix tests lower revenue, higher costs and higher rates against 2029 DSCR. The stated benchmark is above 1.25×.

Prudent · revenue −10%1.92×
Above threshold
Prudent · revenue −15%1.66x
Above threshold
Costs +10%1.91x
Above threshold
Rates +100 bps2.04x
Above threshold
Stress · revenue −25%1.00x
Below threshold
Severe combined stress · revenue −28%0.41x
Below threshold
Transparent interpretation

A 15% revenue decline retains DSCR of 1.66×. The most severe scenarios fall below the 1.25× benchmark and would require corrective action. They do not represent the central scenario.

Portrait of Edgard
Guest experience & sales
« A central scenario is meaningful when it withstands revenue declines and identifies corrective measures. »
Edgard
06

Sensitivities

Exit multiple and property appreciation

The matrix tests five-year gross returns against the operating company valuation multiple and annual property appreciation. The central scenario assumes 4.5× and 1.5%, respectively.

Operating company multipleProperty appreciation5-year MOIC5-year gross IRR
3.5×0%2.01×16.40%
3.5×1.5%2.22×16.98%
4.5×0%2.26×17.38%
4.5× · central1.5%2.14×17.29%
5.5×3%2.27×18.76%

Indicative, non-contractual projections. Valuation, liquidity, distributions, MOIC and IRR are not guaranteed; results depend on operations, financing and market conditions.

07

Key considerations

Six disciplines protect the financial trajectory

01

Property value

LTV assumes a €3.3m post-works value, subject to independent appraisal.

02

Works budget

Firm quotations, contingencies and construction monitoring protect total cost and timing.

03

Ramp-up

Pre-sales and joint occupancy/ADR management support debt coverage.

04

Liquidity

The cash threshold is €150k; projected prudent minimum cash is €196.4k at M+2 and €178.4k with VAT refunds at M+3. The optional €100k VAT facility is outside permanent financing.

05

Debt

Amount, rate, grace period, security and covenants remain subject to definitive banking documentation.

06

Monitoring

DSCR, cash, costs and revenue are compared monthly with the reference scenario.

OverviewBalance, coverage, discipline

The structure combines a substantial equity contribution, contained leverage and long-term debt. Property value, budget compliance and ramp-up remain the main variables to establish and monitor.

Discuss the investment← Return to menu